Supervising the implementation of the 60+800 km Chekodar bridge

Implementation of Chekoder Bridge operation located at km 60+800 plot 4/B of Mashhad-Sarkhes axis

Location: Razavi Khorasan province - Mazdavand city

Client: The parent company specializing in the construction and development of transportation infrastructures in the country

Contractors: Tous Amer Construction and Road Construction Company

Technical Specifications

3 foundations have been made

12 bases has been implemented and completed

The coastal wall is 194 meters long

The foundations have been implemented and completed

26 meters of the hand wall has been completed out of 79 meters

4 spans of 21 meters

The length of the bridge is 84 meters

28 drilling piles has been completed

2 piles and wall piles has been done